Phase: Final Design
Location: Westmoreland County
Anticipated cost: $200-250 million

Project Schedule

Preliminary Design:
2020-2024
Environmental Clearance:
August 2024
Right-of-way Acquisition:
2024-2027
Final Design:
2024-2027
Construction:
2027-2030

Project Overview

Design Underway

Preliminary Engineering for the project began on Sept. 16, 2020. The project will consider mainline improvements along Interstate 70 (I-70) in the project area that includes the Lover interchange (Exit 36). The purpose of this reconstruction project is to:

  • Improve this section of I-70 in accordance with PennDOT District 12’s I-70 Modernization Plan that will provide a consistent typical section along the larger I-70 corridor, in Washington and Westmoreland counties.
  • Address system linkage, structure, and pavement needs.

This project will:

  • Reconstruct all pavement
  • Provide two 12-foot lanes in each direction
  • Widen the median to 10 feet
  • Include 12-foot shoulders on each side of the roadway
  • Provide a swale or buffer beside the shoulder

The Project Team selected the alternative that includes building a new full diamond interchange.

    The project team developed an Alternatives Analysis report which evaluated each of the alternatives related to safety, traffic, environmental, and right-of-way impacts, costs, and public involvement. The report was approved by PennDOT and the Federal Highway Administration (FHWA) on June 22, 2022 and recommended a new full diamond interchange at the Lover Interchange (Exit 36).

    Key features of the project:

    • The Lover Interchange (Exit 36) will be reconstructed as a full access diamond interchange.
    • The bridge that carries Twin Bridges Road over I-70 at the interchange will be raised approximately 4.5 feet to provide adequate clearance over I-70 and have three lanes with one lane in each direction and a center turn lane.
      • The existing bridge was built in 1958 and is in poor condition with substandard vertical and horizontal clearance.
      • The existing bridge currently has a daily traffic volume of 2,000 vehicles and traffic data indicates that most drivers who use the bridge are accessing the interchange and I-70, and that most traffic comes from the south side of I-70.

    Project Mapping

    View project mapping to learn more details about this area.

    PennDOT Contact

    Name: Sean Sepe, P.E.
    Organization: PennDOT District 12
    Title: Project Manager
    Phone: 724-439-7322

    Design Contact

    Name: Patrick B. Richter, P.E.
    Organization: SPK Engineering
    Title: Project Manager
    Phone: 724-439-1600

    Preliminary Engineering Noise Activity & Next Steps

    The project complies with federal noise regulations, which mandate assessing and mitigating traffic noise. To date, a Preliminary Design Noise Analysis and a Noise Technical Report have been completed. Potential locations for noise walls will be finalized during the project’s final design phase. The noise mitigation process will determine if noise mitigation is warranted, feasible, and reasonable for impacted areas. Public involvement is essential throughout noise-related discussions, particularly concerning the potential locations, heights, and lengths of proposed noise walls. Meetings will be held with property owners impacted by each potential noise wall location.

    Public Engagement

    OCTOBER 2024

    In October 2024, PennDOT conducted a Stakeholders Meeting with representatives of various community segments to provide a project status update, discuss final design activities, and review the project schedule. View presentation here.

    MAY 2023

    A public meeting was held on May 18, 2023 to provide an opportunity for general public review and feedback on the recommended alternative. Common concerns included noise, property, safety, roadway, drainage, and pedestrian access.

    SEPTEMBER 2021

    In September 2021, PennDOT conducted a Stakeholders Meeting with representatives of various community segments to provide a project status update and solicit feedback on the CCA findings.

    EARLY 2021

    A Community Context Audit (CCA) was conducted in early 2021 to discuss the project with state, county, and local public officials, the PA Turnpike Commission, emergency service providers, business owners, schools, and other stakeholders to gather input about local interests in the project. The information gathered during these interviews is used by the Project Team to inform project development.